Case study
An anonymised emergency healthcare network mobilised in three days and delivered by 20 engineers working day and night shifts.
LGN delivery framework
Client-supplied project evidence
Client-supplied project evidence
Client-supplied project evidence
The challenge
The brief required more than 1,800 Cat6 outlets, eight communications cabinets linked by fibre, cabinet racking, patching, testing and support for go-live. Pandemic distancing, face coverings, a congested multi-trade environment and an immovable operational deadline shaped every decision.
LGN response
LGN organised two 12-hour shifts, coordinated engineers around other trades and treated cabinets, copper, fibre and certification as one package. Work was tested and closed progressively rather than left to the final hours.

Outcome
The complete physical network was handed over in five days. Client names remain withheld because of the commercial delivery chain and the sensitive circumstances. The case demonstrates rapid mobilisation and programme control, not a general promise that every 1,800-point project can be delivered in the same period.